Subdivision

Kotuku Park Subdivision Stage 4

Project Overview: Earthworks, drainage and roading for new subdivision in Paraparaumu, including cut to fill, import and place sand and topsoil strip, stockpile and respread

Interesting Points

  • 14,000m3 earthworks

  • Drainage included all stormwater, sewer and water

  • Drainage was up to 3.5m deep

  • 300m of roading

  • 580m2 exposed aggregate paths

  • 50m2 timber retaining walls

  • 145m2 of concrete block retaining walls

  • timber fencing