Roading
Kaitoke to Te Marua Realignment
Project Overview: 5km of State Highway 2 realignment. New alignment crossing existing highway several times. Retaining wall construction with Geogrid retaining, Gabion basket walls, vertical concrete block wall, interlocking concrete panel walls. Drainage included with large diameter culvert pipes down live streams. Drainage on very steep grades with unusual change of direction bends.
Earthworks
250,000 m3 cut to fill
400,000 m3 cut to waste
Imported fill brought in
3 fills were preloaded for 6 months
Cuts up to 40 m high