Peka Peka to Otaki Expressway Rail Works

Project Overview: Peka Peka to Otaki Expressway Rail Works December 2018/January 2019 – 3 day window to complete 2x concurrent work areas.  Worked both areas on 24 hour shifts for this period.

Block of line main trunk line north of SH1 bridge in Otaki involved:

  • Remove 150m of trackset,

  • excavate unsuitable 6m deep,

  • replace to subgrade 150mm deep,

  • place basecourse to grade,

  • dressed with 20mm topping,

  • use GPS grader for final trim on transitional curve and straight,

  • place ballast to grade,

  • lifted track set back in.

Block of line work at Otaki Station:

  • Lift trackset out,

  • excavation as above but 3m deep and amongst a lot of services,

  • backfill,

  • drainage,

  • place ballast to grade,

  • lift trackset back in.