Project Overview: Bulk earthworks to remove slip above Waterfall Road as it was a hazard. Extremely steep site required experienced operators. Once the top of the slip was cut off operators accessed site by a steep access track from Waterfall Road. Slip started 50m above the road below. Close cooperation between client, landowner and Goodmans to ensure the works met the requirements of the parties. Waterfall Road had been closed for a number of months prior to the works being confirmed. There was a stream of cultural significance adjacent to the road and bunding on the edge of the road was installed to protect the stream from material fall in.
Interesting Points
Cut bench above the slip to create a platform for rock anchor installation
Create bench to design, materials sent down a chute and re-handled at the base of the slip
9,400m3 off the face of the slip and re-handled at the base to cart offsite to Council landfill
Excavators used to excavate and pass materials from slip face to bench then excavate and send material down chute.