Blue Bluffs Otaki Slip Repair

Project Overview: Bulk earthworks to remove slip in Otaki Gorge 13km inland from SH1. Road was closed completed and site barricaded. Catch pit constructed to hold excavated materials to minimise run-off from site. Concrete Barriers also used.

Earthworks

  • 75,000m3 excavated and cleared from slip

  • Majority of material transported to local forestry sites and used to create skid sites and access roads. Negotiations for this by Goodmans.

  • Earth chute designed to remove excavated material from the slip face safely.

  • Design of works by Goodmans surveyors